Tendering Services

Available to provide fast, technical and commercial advice.

Pre tender surveys.

Preparation of outline specifications.

Evaluation of enquiry specifications and drawings to highlight potential issues.

Preparation of technical tenders.

Negotiation with suppliers and subcontractors to ensure best prices are obtained.

Preparation of commercially competitive tenders.

External design support.

 

Electrical Services

Lighting & Emergency Lighting.

Low voltage electrical installation/maintenance.

Routine electrical maintenance & fault finding.

Electrical inspection & testing/Thermal image surveys.

Metering/Monitoring of electrical supplies.

Installation of control systems.

 

Mechanical Services

Electrical & Mechanical Plant Installation.

Commissioning & Maintenance.

Heating System Installation.

Commissioning & Maintenance.

Ventilation Ductwork Installation.

Cleaning.

Commissioning HVAC Services Including:

Water Treatment.

O&M Documentation.

Commissioning Management.

 

Construction & Building Services

General Building Maintenance / Reactive Maintenance.

General Groundwork's.

Drains & Sewer Cleaning / Inspection.

 

Additional Services

Project Management.

Ability to Subcontract.

 

Recent Projects:

 

"Greater Manchester Fire & Rescue"

 

"Parklands, Speke, Liverpool"

 

"QE2 Law Courts Liverpool"

 

We cover:

 

 

Atherton

Wigan

St Helens

Bolton

Leigh

Lancashire

Cheshire

Warrington

Liverpool

Salford

Manchester

Greater Manchester

Merseyside

North West

Ascot Services UK Ltd: The Sawmills, 52 Rosedale Avenue, Atherton, Manchester M46 0DZ

Ascot Commissioning Services UK Ltd: 153 Elliot Street, Tyldesley, Manchester M29 8FL

Home | Company | Services | Management  | Verification | Certifier

HVAC C & T | O & M Manuals | Water Treatment | Contacts

 

enter

© 2012 Ascot Services UK Ltd - enquiries@ascotservices.com - home - services - commissioning - contact - Ascotservices.com by

 

 

 

Air Conditioning Systems

 

1. Fan and motor speeds.

2. Full drive set details.

3. Motor running amps.

4. Air pressure drop readings across:

a) Fan

b) Filter sets

c) Heater batteries

d) Cooling coils

5. Total plant air volumes

6. Branch volumes

7. Terminal air volumes.

 

HVAC COMMISSIONING & TESTING:

Vent Commissioning

The supply of engineers to carry out the commissioning at a dedicated contract as detailed below:

We will include in our commissioning reports the following where practical:

Air and Water Systems

 

1. Belt tensions checked and left correctly adjusted.

2. Drive sets are secure and alignment is correct.

3. Impeller is secure on shaft and free to rotate.

4. Air handling unit filters & pump strainers are in position & clean.

5. Motor and fan bearings are lubricated.

6. All power wiring is complete

7. Suitable fuses and overloads are fitted.

8. Fan/pump rotation is correct.

9. Monitor motor start-up and running currents.

 

Water Distribution

 

1. Pump and motor speeds.

2. Full drive set details.

3. Motor running amps.

4. Pump duty with system on full load.

5. Recording and setting of pressure drops on flow measuring valves, orifice plates, venturis and through all items of equipment where a pressure drop is required and test points are available.

Air Distribution System

 

1. All airways are clean and dust free.

2. All ductwork is airtight and free from leaks.

3. Duct & grille dampers are set in the full open position checked for free & adequate movement.

4. Fire dampers are checked and left fully open.

5. Access is available to all dampers.

 

Water Distribution System

 

1. System is watertight.

2. System has been flushed, filled and properly vented.

3. Control and non-return valves fitted correct way round.

4. All normally open valves are open and normally closed valves are closed.

5. Make-up tank is filled and pipework to system is open.

6. Strainers have been removed and cleaned.

7. Pressurisation unit is operational.

Information required by our engineers prior to arriving on site is as follows:

 

• Full set of drawings

• Relevant extracts from, or a complete copy of, the specification.

• Wiring diagrams for all equipment showing control circuits and interlocks.

• Manufacturers’ literature for all equipment.

• Design volumes for all fans and grilles, pumps, regulating valves, control valves and equipment.

• Pump and fan characteristic curves.

Commissioning is defined in CIBSE Commissioning Codes A, C & W as “The advancement of an installation from a stage of static completion to full working order to specified requirements.

Note 1. Commissioning shall include the setting to work and regulation of an installation.

 

(a) Setting to work: The process of setting a static system into motion.

 

(b) Regulation: The process of adjusting the fluid rates of flow in a distribution system within specified tolerances.

Note 2. Commissioning shall be deemed complete at the “conclusion to regulation “.